What costs go into a construction job?
Five groups of direct costs, plus overhead:
- Direct labor. Hours worked on the job times each person's pay rate, plus labor burden (next section).
- Materials. What was bought for the job or taken from your stock and used on it, at what it cost you, including delivery.
- Subcontractors. What you pay the electrician, plumber or drywall sub for this job, including change orders.
- Equipment. Rentals, plus a rate for your own equipment if you want owned machines to show up in job cost.
- Other direct expenses. Permits, dumpsters and disposal fees, fuel for job runs, job-specific insurance or bonds.
- Overhead. Costs that keep the company running but belong to no single job: office, office staff, trucks, insurance, software. They are allocated to jobs by a rule.
A useful test for whether a cost is direct: would you have spent it if this job did not exist? If not, it belongs on the job.
How do you calculate labor cost with burden?
Start with wages: hours on the job times the pay rate. Then add the labor burden, the costs you carry on top of every dollar of wages. Common pieces:
- Employer Social Security and Medicare: 6.2% and 1.45% of wages, with Social Security capped at a wage base of $184,500 for 2026 (IRS Topic 751).
- Federal unemployment (FUTA): 6.0% of the first $7,000 per employee per year, reduced by a credit of up to 5.4% for state unemployment taxes paid (IRS Topic 759).
- State unemployment tax, which varies by state and by your company's history.
- Workers' compensation, which varies widely by state and by trade classification.
- General liability premiums tied to payroll, health insurance, retirement contributions, paid holidays and vacation, if you offer them.
Because workers' comp and state taxes differ so much, there is no universal burden percentage. Work out your own: add up a year of these costs and divide by a year of field wages. The result is your burden rate, and it can be very different for a framing crew and a finish carpenter.
The free labor cost calculator takes crew size, hours, rates and your burden percentage and shows labor as a share of the contract.
How do you allocate overhead to a job?
Pick one simple base and use it on every job. The most common:
- Percentage of direct cost. Last year's overhead divided by last year's total direct cost. If overhead was $180,000 and direct costs were $1,200,000, overhead is 15% of direct cost.
- Per labor hour. Overhead divided by field hours. Better when your jobs differ a lot in material content.
Overhead does not change what a job spent, but it changes whether the job actually made money. A job that shows 18% before overhead and 3% after is not one you want more of.
What does a job cost look like in dollars?
A kitchen remodel with a contract value of $48,500. The crew: one lead carpenter at $32 an hour for 120 hours and two helpers at $22 an hour for 110 hours each. In this example the company's burden rate is 25%; yours will be different.
- Wages: 120 × $32 = $3,840, plus 220 × $22 = $4,840, total $8,680.
- Burden at 25%: $2,170. Labor cost: $10,850.
- Overhead at 15% of direct cost.
| Cost | Budget | Actual | Variance |
|---|---|---|---|
| Labor (with burden) | $9,800 | $10,850 | +$1,050 |
| Materials | $13,500 | $14,200 | +$700 |
| Subcontractors (electric, plumbing) | $8,300 | $8,300 | $0 |
| Equipment (rentals) | $1,000 | $1,150 | +$150 |
| Other direct (permit, dumpster) | $900 | $1,050 | +$150 |
| Direct cost | $33,500 | $35,550 | +$2,050 |
| Overhead (15%) | $5,025 | $5,333 | +$308 |
| Total cost | $38,525 | $40,883 | +$2,358 |
| Profit on $48,500 | $9,975 (20.6%) | $7,617 (15.7%) | −$2,358 |
The job still made money, but five points less than planned, and half of the gap is labor. That is the question to ask: were the hours estimated too low, or did something on site cost extra time? The answer changes the next bid.
How do you track budget vs actual while the job runs?
Set the budget by the same cost groups you will track, then compare weekly. A few habits make the comparison worth having:
- Same categories in the estimate and the actuals. If the estimate has "Framing labor" and the books have "Payroll", nothing lines up.
- Record costs when they happen. Receipts in a glovebox for a month mean you learn about the overrun after the job is over.
- Watch percent of budget used against percent complete. 80% of the labor budget spent on a job that is half done is the early warning.
- Log change orders separately. Extra work the client approved should raise both the budget and the contract value, or it will look like an overrun.
What are the most common job costing mistakes?
- Leaving out burden. Costing labor at the wage alone understates it on every job.
- Hours on the wrong job. A crew that moves between sites and records one job per day spreads cost randomly. See how to track hours across multiple job sites.
- Mixing cost and price. What you bill the client per hour is not what the hour costs you. Keep both, separately.
- Materials bought for one job and used on another. Move the cost when the material moves, or one job gets a gift and the other a bill.
- No overhead. Jobs that look profitable before overhead can lose money after it.
- Costing once, at the end. By then it is history. The value is in seeing it while you can still act.